Budget estimate
Lagos, Nigeria
Drop in your architect’s drawings: areas, storeys, heights and walls are measured and carried into the form.
PDF or images (JPEG, PNG, WebP), 10 files at most.
The economic capital and the main port, and the dearest place in the country to build: ₦150,000 to 230,000/m² for standard residential against ₦130,000 to 185,000 in Abuja. Land, the congestion at Apapa and sheer demand cost more than being at the port saves.
The sum of every storey, measured over the walls.
Stacking storeys lowers the cost per m²: less foundation and less roof.
Each additional bathroom adds to the plumbing.
Driven entirely by the ground. On sandy, sloping or low-lying sites a soil survey is not optional.
Stable bearing ground. The most common solution in the DRC.
The 15 cm block is the DRC load-bearing standard. The 10 cm block is for partitions only.
The standard load-bearing wall unit in the DRC, for one or two storeys.
A column-and-beam frame is the norm above one storey, or wherever you want large openings.
Concrete frame with block infill. The regional standard.
A ventilated void protects against rising damp, which is common in the rainy season.
Slab cast on compacted hardcore. The cheapest option.
A flat slab lets you add a storey later, but costs close to double a sheet roof.
The most widespread solution in the DRC: light, quick to fix, cheap.
Security grilles are included in every option, as they are the norm in the DRC.
Cheapest. Needs regular maintenance and termite treatment.
Double glazing only pays off alongside permanent air conditioning.
The local standard.
Under a sheet roof, the ceiling is what makes the difference to thermal comfort.
The common, economical solution.
Ceramic tiling dominates; a smoothed screed is still common in self-build.
The default choice, wide price range.
Wet-room tiling is counted separately from the general wall treatment.
The standard, inside and out.
The public network is intermittent in most neighbourhoods: plan for storage.
Full independence. The most widespread solution outside the city centre.
There is almost no sewer network in the DRC: a septic tank is the rule.
The normal solution for a house.
A solar water heater pays back quickly wherever power is dear or scarce.
Common in economy housing.
A good ceiling and cross-ventilation often beat an undersized air-conditioning system.
Cheap and very effective in this climate.
A grid connection alone is rarely enough: outages are a daily event across most of the countries covered.
Changeover, batteries and priority circuits.
Slope, water, rock and fill: the four things that blow a foundation budget.
Minimal earthworks.
If a lorry cannot unload on the plot, everything is carried by hand.
Delivery at the work face.
Self-building saves the contractor’s margin, at the cost of your time and the risk.
A single point of contact, 10–20% margin.
10% is the sensible minimum in the major cities, 15% in the provinces.
Tick this if you are using a formal contractor who charges VAT.
Leave at 0% if you are budgeting your own project, because the base rates already include a builder’s margin. Only turn it on if you are pricing a client quotation.
Labour is the softest number in the estimate. These three choices genuinely move it, and they compound: a site with no supervision, learning the technique, and hard to reach costs far more than the three penalties added together.
Add anything this tool does not know about: an unusual material, a firm supplier quotation, a one-off item. Your lines follow contingency, margin and VAT like every other.
The rate per m² used here already includes all four: the figures below show what it assumes. If you have a real quotation, enter it and it will replace the estimate.
The people who build it: labourers, masons, carpenters, steelfixers, electricians, plumbers, tilers, painters and the site foreman.
Enter the total labour figure from your quotation, charges included, for the whole build.
Equipment hired or written down on site, and the fuel that runs it.
Add up hire charges, fuel, and depreciation on plant you already own.
Getting materials to site, including the last kilometre, which is often the dearest.
Enter the total delivery figure from your supplier quotations, clearance included if you import.
What you pay to be allowed to build and to have it properly designed. Nearly all of it falls due before the first block is laid.
Add up signed fee letters and any charges the commune has already quoted you.
Your figure replaces the estimate rather than adding to it, otherwise you would pay for the same item twice. Leave blank anything you do not know.
No saved projects. Give this one a name and save it, and it will be here.
Every figure is recalculated now, at today’s prices. Nothing is frozen at the moment it was saved.
Saved in this browser only, not on a server. To pick an estimate up on another device or send it to someone, use the share link: it carries the whole project.
The prices below are market averages. If you have your own suppliers or crews, replace them: your rates are saved in this browser and reused on every visit.
Initial verification, per circuit (IEC 60364-6)
per circuit
Isolation valve, per fixture
per valve
Wall coping
per metre
Damp-proof course
per metre
Gate lock and drop bolt
per set
Formwork, per m² of contact area
per m² formed
Binding wire (for tying reinforcement)
per kg
Weep hole (75 mm PVC sleeve through the wall)
per weep hole
Filter fabric (behind the wall)
per m²
Concrete curing (sheeting and water, 7 days)
per m² of surface
Movement joint (backer rod and sealant)
per metre
Consumer unit, per way (three phase)
per way
Supply cable (3 × 10 mm²)
per metre
Copper supply pipe (ø 22)
per metre
Pressure PVC supply pipe (ø 25)
per metre
Stair nosing (aluminium or PVC)
per metre
Exterior paint (20 L drum)
per drum
Primer or sealer (20 L drum)
per drum
Door ironmongery (lock, handle, 3 hinges)
per set
Electrical point, surface mounted
per point
Ridge capping (pre-folded)
per metre
Roofing fixings (box of 100)
per box of 100
Grey cement (50 kg bag)
per bag
Scaffolding, erect and hire
per m² of elevation
Slab propping
per m² of soffit
Setting out
per metre of perimeter
Mixing water, delivered
per m³ of concrete or mortar
Hand excavation, ordinary ground
per m³
Washed crushed sand (0/5)
per m³
Sharp sand
per m³
Crushed granite
per m³
Rubble stone
per m³
Reinforcement bar
per tonne
Steel section (IPE, HEA)
per tonne
Cement block, 9 inch (225 mm)
each
Cement block, 4 inch (100 mm)
each
Cement block, 6 inch (150 mm)
each
Cement block, 8 inch (200 mm)
each
Half block 15 × 20 × 20
each
Half block 20 × 20 × 20
each
Hollow block, 10 inch (250 mm)
each
Solid block, 6 inch (150 mm)
each
Stabilised compressed earth block
each
Fired brick
each
Mud brick
each
Structural timber
per m³
Galvanised sheet (2.40 × 0.90 m)
per sheet
Fibre-cement corrugated sheet
per sheet
Roof tile (stone-coated)
each
Floor tiling
per m²
Tile adhesive (25 kg bag)
per bag
Tile grout
per kg
Emulsion paint (20 L tin)
per tin
Polythene damp-proof membrane (300 µm)
per m²
Damp-proof course roll (23 cm)
per linear metre
SBS bitumen membrane 4 mm
per m²
Liquid waterproofing (per coat)
per m² per coat
Cementitious tanking slurry, per kg
per kg
PVC ceiling panelling
per m²
Plasterboard / POP
per m²
Skirting
per metre
Metal door with frame
per door
Timber door with frame
per door
Glazed aluminium window
per m²
Louvre window
per m²
Burglar bar
per m²
Stair balustrade
per metre
Gutter
per metre
Rainwater downpipe
per metre
Supply pipework (PPR ø 25)
per metre
Waste pipework (PVC ø 110)
per metre
Plumbing point (WC + basin)
per point
Sanitary ware (WC, basin, taps)
per set
Electrical point (socket or light)
per point
Distribution board, per way
per way
Earth electrode
per installation
Supply cable (4 × 10 mm²)
per metre
Storage tank, per litre
per litre
Submersible pump
each
Tank tower, per metre of height
per metre
Electric water heater, per litre
per litre of capacity
Solar water heater, per litre
per litre of capacity
Instantaneous gas water heater
each
Generator, per kVA
per kVA
Solar PV, per Wp
per Wp
Battery, per nominal kWh
per kWh
Hand-drilled borehole, per metre (to 40 m)
per metre
Rig-drilled borehole, per metre (beyond 40 m)
per metre
Labourer
per day
Mason
per day
Carpenter / formworker
per day
Steelfixer
per day
Electrician
per day
Plumber
per day
Painter
per day
Tiler
per day
Site foreman
per day
Boundary wall and gate
each
Most likely budget
32,451,000 ₦
Range: 21,693,000 ₦ – 43,208,000 ₦
This budget starts from a cost per m² for "Standard", adjusted for Lagos, for the building type and for a single storey, then adds your options and a contingency. Structural quantities and member sizes follow the Eurocodes; prices, lead times and risks follow Congolese reality. Every price on the site says whether it is sourced, computed or estimated.
Savings identified 2,347,000 ₦
1 thing to settle before costing this seriously, and about $1,738 of savings identified.
Public supply is run by state water boards and reaches only a minority of urban plots. A private borehole is not a comfort option here, it is the ordinary water source for a house: costing starts from drilling rather than from a connection. A borehole and tank are the rule, not an option, and retrofitting them costs more than designing them in now.
Delivered to site this route costs $12.30 against $21.30 locally, roughly $964 on this project. Lead time 0–2 days.
Delivered to site this route costs $13.50 against $18.50 locally, roughly $265 on this project. Lead time 0–2 days.
Delivered to site this route costs $186.00 against $266.00 locally, roughly $245 on this project. Lead time 0–2 days.
Delivered to site this route costs $696.50 against $891.50 locally, roughly $239 on this project. Lead time 0–2 days.
Delivered to site this route costs $35.30 against $54.30 locally, roughly $25 on this project. Lead time 0–2 days.
About 63 m of wall to treat at 150 mm above finished ground (EN 14967), roughly $121. It is the most expensive saving in building: without it damp climbs the masonry and you re-render and repaint the whole house after one wet season.
River sand delivered here often carries silt, clay or, near the coast, salt. Silt stops cement paste bonding and salt corrodes reinforcement from the inside. Do the jar test before accepting a load: sand and water in a jar, left to settle for an hour; more than 5% of fines sitting above the sand and you refuse the truck or have it washed. It is the commonest reason concrete never reaches its strength, and it is invisible at the pour.
Without a soil test the bearing capacity used here is an assumption, and so is the footing priced from it. Two hand-dug trial pits and a penetrometer cost a few hundred dollars; underpinning a cracked house costs tens of thousands. Dig at least 1.5 m below the intended founding level, and be wary of fill: many urban plots are old gullies that were tipped into.
Materials are quoted in dollars while wages and much local work are paid in local currency. Over a twelve to eighteen month build, a slide in the rate moves the budget without anything changing on site. Two simple protections: buy the heavy items early rather than spreading them, and agree the currency and the reference rate with the contractor in the contract, not at payment time.
For 5 people, 650 L a day with two days of storage. The pump works against 108 m of head including drawdown and the tower, about 0.06 kW. Drilling is estimated at $1,200 to $8,000. Ask what depth the neighbour’s borehole hit: it beats any table.
Masonry materials are bought where you build. Long-haul freight overtakes the price gap quickly, bags break or get wet in transit, and it is the local merchant who will cover you on the next hundred bags. The prices used here are Lagos prices.
Your estimate comes to $200 per m². On the Congolese market this kind of property changes hands between $500 and $3,636 per m² finished (listing analysis, August 2025). The two figures are not directly comparable: a sale price carries the land, the connections, the permits and a developer’s margin, none of which is in a build cost. So building comes out cheaper per m², but the gap is not a gain: it is what you have to find in land, fees and your own time.
Maximum demand 8.0 kVA plus a starting margin gives the standard 15 kVA rating. Estimated consumption 25 kWh a day. Cheapest is the chinese (entry level) route, from $2,250.
For 5 people, per EN 12566-1, giving 138 hours of retention. The field is sized for loam, and it is the field that fails, not the tank. Run a percolation test before siting the house: on clay no soakaway will hold and you will need a sand filter or a package plant. Allow the space on the site plan from the start.
The day rates in this tool come from the statutory scale (National Minimum Wage Act 2024), category by category. A quotation that goes below them is not cheaper, it is unlawful, and the exposure is yours.
These remarks are computed from your choices and the country data. They do not depend on any external service.
| Item | Share | Low | Typical | High |
|---|---|---|---|---|
| Design, drawings and permitsArchitect, working drawings, soil survey and building permit. | 4% | 713,000 ₦ | 953,000 ₦ | 1,193,000 ₦ |
| Earthworks and foundationsClearing, excavation, footings, ground beam and ground-bearing slab. | 13% | 2,318,000 ₦ | 3,098,000 ₦ | 3,877,000 ₦ |
| Masonry and structureCement blocks, reinforced concrete columns and beams, ring beams, floor slabs. | 22% | 3,923,000 ₦ | 5,242,000 ₦ | 6,561,000 ₦ |
| Roof structure and coveringTimber or steel roof structure, sheet or tile covering, gutters and downpipes. | 11% | 1,961,000 ₦ | 2,621,000 ₦ | 3,281,000 ₦ |
| Doors and windowsDoors, windows, glazing, security grilles and ironmongery. | 9% | 1,605,000 ₦ | 2,144,000 ₦ | 2,684,000 ₦ |
| Plumbing and sanitary wareSupply and waste pipework, septic tank, sanitary fittings, water tank. | 8% | 1,426,000 ₦ | 1,906,000 ₦ | 2,386,000 ₦ |
| Electrical installationWiring, distribution board, sockets and light points, earthing, connection. | 7% | 1,248,000 ₦ | 1,668,000 ₦ | 2,088,000 ₦ |
| Plaster, screed and floor finishesInternal and external plaster, screeds, floor tiling and wall tiling. | 13% | 2,318,000 ₦ | 3,098,000 ₦ | 3,877,000 ₦ |
| Painting and final finishesPreparation, primer, internal and external paint, final clean. | 7% | 1,248,000 ₦ | 1,668,000 ₦ | 2,088,000 ₦ |
| External worksYard, driveway, drainage, water and power connections at the plot boundary. | 6% | 1,070,000 ₦ | 1,430,000 ₦ | 1,789,000 ₦ |
| Works subtotal | 17,830,000 ₦ | 23,827,000 ₦ | 29,825,000 ₦ | |